#OT022 - Water ponding on facility floor
Accepted Task
on 23 Apr 2020, 2:30pm
Due on 23 May 2020, 2:30pm
Submitted
on 23 Apr 2020, 2:30pm
by Eugene
Assets | Book From | Return Date | Booked To | |||
---|---|---|---|---|---|---|
![]() |
002 - 19" Toolbox | 23 May 2020, 3:20pm | 24 May 2020, 3:20pm | Daniel | ||
![]() |
003 - 12 Steps Ladder | 23 May 2020, 3:20pm | 24 May 2020, 3:20pm | Daniel |
- Company 1 is a better comparison in pricing; and
- Company 1 able to provide a full report of all the faulty equipment.
- Company 2 is ...
- Company 3 blah blah...
Budgeting
Carry Forward Balance
RM40,000.00
Spent
RM1,000.00
Remaining
RM39,000.00
Start Work
on 28 Sep 2023, 3:00pm
Estimated complete on 23 Oct 2023, 3:00pm
Person in charge: Ivan, 012 345 6789
03 462 4869
#BC-00004
Start Work
on 28 Sep 2023, 3:00pm
Estimated complete on 23 Oct 2023, 3:00pm
Person in charge: Ivan, 012 345 6789
Fatimah